Permits and licenses

Land-use license in Monterrey: how it is filed

Before you build, lease or open a business on a property you need to know what is allowed there. In Nuevo León that is settled in several municipal stages, and "land use" can mean more than one document. Here are the differences and the filing process in Monterrey.

TAX AS · November 6, 2026

Who authorizes it

Under the Human Settlements, Territorial Planning and Urban Development Law of the State of Nuevo León, municipalities authorize or deny feasibility reports and land-use, construction and building licenses, according to urban development plans and their own regulations. In Monterrey the Secretariat of Sustainable Urban Development (Secretaría de Desarrollo Urbano Sostenible) handles it.

The stages and what they are called

The law orders the process like this: land-use feasibility, general architectural design guidelines, the architectural project, which constitutes the land-use license, the executive project, which constitutes the construction license, and the building-use license. In other words, the land-use license is not a generic paper saying "a restaurant is allowed here": it is the authorization of the architectural project.

Feasibility and the land-use license

Feasibility determines a property's land use and density under the municipal plans. To request it you file an application, proof of ownership or possession, a location plan, the intended use, payment of fees and current property tax. The land-use license asks, among other documents, for the feasibility and guidelines decision, the architectural drawings with floor plans, elevations and sections, and extra studies in some cases: mobility if the project needs more than 50 parking spaces and the site is not in an authorized subdivision, environmental impact, geophysical studies in risk zones, and water, drainage and electricity feasibility for buildings over 1,500 square meters.

The building-use license

If the building already exists and you will use it for anything other than a single-family home, you need the building-use license, which is issued after an inspection confirming the building is fit for that activity. Changing a building's use only takes a notice, except for businesses with alcohol sales or production, hazardous chemicals, fuels and high-risk businesses, which need a new license.

Deadlines set by law

With a complete and correct application, the authority must answer in 5 business days on feasibility and in 10 business days on the land-use or building-use license. In practice, what drags the process out is an incomplete file or open observations. The law also says feasibility, guidelines and the land-use license do not expire.

How the process works in Monterrey

According to the procedure the municipality publishes (May 2023 version), you book an online appointment and go to a service window, where they check the documents. If complete, the file enters the system, a start-of-process payment order is generated, and opinions are requested from the technical areas along with an inspection report. Observations are notified to the applicant; if they are not addressed, a notice with 20 business days to complete or correct is issued, and if that is not addressed either, the file is dismissed. The process fee is paid before the ruling is delivered. The maximum ruling time the procedure states is 10 business days.

Why it matters for other permits

The land-use and building-use licenses are prerequisites for other filings. For the municipal anuencia and the liquor license, for example, the zoning certificate, the land-use license and the building license are all required. If the business type does not fit the property's permitted use, the rest of the project falls apart.

What to check before committing money

Request feasibility before you buy, lease or commission the project. It tells you the permitted use and density, and shows early whether a change of use is needed. Rules change by zone and by urban development plan, so each property is reviewed on its own. This is useful for foreign investors choosing a site for a plant, office or store in Monterrey.

This article is for information only and does not replace a review of your case. Tax rules change: check the publication date.